Interrupts

This text is based on chapter 11 of Booklet 4: Controlling Project Risk by Design (pdf, 586 kb)

One of the potential risks of wasting time is Interrupts. In Evo, we only work on planned tasks, never on undefined tasks. In case a new task (or a new requirement) suddenly appears in the middle of a Task Cycle, we call this an Interrupt.
Assume the boss comes in and asks us to paint the fence. We don't say Yes, but we also don't say No. After all, painting the fence may be more important than anything we have currently planned, if an important customer would turn his heels when he sees the shabby fence. Instead, we follow the Interrupt Procedure:

But if we do the new thing in between, isn't this delaying the work we originally planned? Yes, of course it is. But we deal with the consequences of the change in the plan. We Act.

If something comes in between (see figure), the rest moves accordingly.
This appears difficult to understand for some people. When a service-desk manager said: "If a customer needs service, the developers should drop their work and immediately help the customer." I said: "OK. But that means that the rest of their work will move." "That's unacceptable! The schedule shouldn't move!" he said.
I replied: "Whether we like it or not, it will move. We better acknowledge it, and see what we can do about it." This event actually made me make this figure.
We don't let things happen randomly, we rather control how they happen. If some requirements become more important than others, the order of what we do should change. Priorities do change all the time, so the thing is to dynamically reprioritize as needed. Revisiting TimeLine will tell us what the consequences will be: What will be done, what will not be done, and what may be done at any FatalDate. We cannot do more than we can do. We don't try to do the impossible. All we can do is making sure that looking back we always rightfully can say: "Nobody could have done it better. Not even us!"

With the Interrupt procedure, we control the risk of wasting time on seemingly important things, as Interrupts often seem more important than they really are.

One of the Magic Questions is "Who is waiting for it?" If you don't get a satisfactory answer, then suggest that you apparently don't have to do it. Saving time isn't that difficult !